AEDC Meets Estate Developers, Seeks Early Power Planning

Follow THISDAYLIVE on GoogleAdd us as a preferred source to see more of our stories in Google
Follow us on Google

• Promises faster connections, improved fault response 

•NERC directs developers to report violations

Emmanuel Addeh in Abuja

The Abuja Electricity Distribution Company (AEDC) yesterday urged real estate developers to engage electricity Distribution Companies (Discos) at the earliest stages of project planning to ensure adequate power infrastructure, reduce connection delays and improve electricity supply to residential estates.

The company said developers must integrate electricity demand assessments, network capacity evaluations, transformer installations and distribution infrastructure into their master plans rather than waiting until construction is completed before addressing power requirements.

It also stressed the need for individual metering of housing units, warning that connecting estates without appropriate metering arrangements could lead to estimated billing, disputes between residents and electricity providers, revenue losses and poor service delivery.

Chief Operating Officer of AEDC, Blessing Ogbe, made the call at the company’s Real Estate Developers Stakeholders Forum in Abuja, where the distribution company outlined a partnership framework aimed at improving electricity delivery to new and existing estates across its franchise area.

Ogbe said reliable electricity had become an important determinant of real estate value, influencing occupancy rates, tenant retention, operating costs and the long-term attractiveness of residential and commercial properties.

He explained that estates with dependable electricity were better positioned to attract quality tenants, sustain business activities and reduce reliance on expensive alternative power sources, including diesel generators.

According to him, AEDC was seeking closer collaboration with developers through early engagement, joint infrastructure development, shared demand forecasting, metering expansion and partnerships involving embedded and renewable energy providers.

The company also identified several challenges affecting electricity delivery to estates, including unclear funding responsibilities between developers and distribution companies, unmetered residential units, poorly constructed distribution networks and renewable energy installations operating outside the grid without clear arrangements for integration.

To address these concerns, AEDC proposed a Partner Estate Charter that would establish commitments on connection timelines, electricity supply and fault response, alongside a dedicated partnership desk to facilitate engagement with developers.

The company, which distributes electricity across the Federal Capital Territory (FCT), Nasarawa, Niger and Kogi States, said it currently serves more than 1.3 million customers, with over 1.13 million metered customers, compared with approximately 650,000 in 2023.

It also disclosed audited revenue of N699.48 billion for the 2025 financial year, while energy traded during the period stood at 4,749 gigawatt-hours.

As part of its proposed framework, AEDC said developers should ensure that every housing unit was metered before occupancy, with meters supplied through the distribution company, Meter Asset Providers or developers and integrated into its Advanced Metering Infrastructure platform.

It also proposed check meters at estate boundaries to reconcile electricity consumption, while estates with solar installations between 50 kilowatts-peak and 1.5 megawatts could explore electricity exports to the distribution network under the 2026 regulations.

The company further advocated the publication of feeder hosting capacities and the consideration of mini-grid arrangements for larger estates and districts.

In her remarks, an official of the Department of Consumer Protection, Nigerian Electricity Regulatory Commission (NERC),  Mercy Ohamuche, reinforced the need for strict compliance with metering requirements, insisting that new electricity connections should not be made without appropriate meters.

She warned that some distribution companies and developers sometimes connected premises under the guise of testing installations, even when electricity was already being consumed, thereby creating room for revenue losses and subsequent disputes.

Ohamuche urged developers to engage AEDC directly, submit the necessary documentation and report any failure to comply with regulatory requirements to NERC through its forum offices across the states.

She also said distribution companies were expected to replace faulty meters, adding that where replacement could not be completed within the period, affected customers should be informed and billed based on their average consumption in accordance with applicable regulations.

The NERC official explained that where a meter was damaged, the distribution company was expected to investigate the circumstances and establish responsibility for the damage before determining who would bear the replacement cost.

She also cautioned against shared metering arrangements, noting that individual metering remained the approved standard for residential connections in estates because shared meters frequently generated disagreements among tenants over electricity consumption and payments.

Earlier, the Chairman of the Abuja Chapter of the Real Estate Developers Association of Nigeria (REDAN), Tony Okoruwa, said inadequate coordination between estate development and electricity distribution planning had continued to create avoidable delays, additional costs and disagreements.

He identified inadequate transformer capacity, delayed connections, poor distribution infrastructure planning and insufficient network capacity as some of the major challenges confronting developers.

Okoruwa called for joint electricity infrastructure assessments, advance notification of major estate projects and better coordination between AEDC engineers and developers’ technical teams.

He said electricity infrastructure planning should take place alongside estate development, rather than after construction, to ensure that power requirements were adequately addressed before residents moved in.