Umahi Orders Speedy Completion of Lagos Bridges, Targets December Reopening of Eko

Follow THISDAYLIVE on GoogleAdd us as a preferred source to see more of our stories in Google
Follow us on Google

Bennett Oghifo

The Minister of Works, David Umahi, has directed contractors handling the reconstruction of Carter Bridge and the emergency rehabilitation of Eko Bridge in Lagos to accelerate work, as the federal government moves to restore two critical links serving some of the state’s busiest commercial corridors.

Umahi, who gave the directive during an inspection of the Eko, Iddo and Carter Bridges, said the 1.98-kilometre Carter Bridge reconstruction had recorded five per cent progress, with four piles completed and a temporary access bridge extended to 230 metres out of the planned 330 metres.

He disclosed the federal government would release 30 per cent of the mobilisation funds within days, while efforts were underway to reduce the original 36-month completion period to between 18 and 24 months.

The minister also assured the reconstruction had been designed with long-term durability in mind, including protective measures aimed at giving the bridge a lifespan of more than 100 years.

“We have directed that when they start the piling, a number of big lumps must be put in place to protect the piles at the seabed. This will reduce scouring and removal of the sand because this piling is deriving its strength from skin friction,” Umahi said.

The Carter Bridge project, according to the minister, requires extensive underwater piling and specialised construction methods because of the difficult soil conditions at the site.

He explained that contractors were using 1.5-metre-diameter casings and deep piles, with some of the piles extending to about 52 metres, while special equipment and divers were deployed to deal with the underwater construction challenges.

Umahi said the contractor had completed an initial stage involving the casing and was proceeding to the next phase, including reinforcement, beam construction, jacketing and the casting of a new pile cap.

He added that post-tensioning tendons would subsequently be installed to connect the pile caps and strengthen the structure.

On Eko Bridge, the minister said the N12 billion emergency rehabilitation became necessary after illegal sand mining damaged an underwater section of the bridge and caused part of its pile cap to collapse.

The rehabilitation involves the installation of four piles to a depth of about 54 metres and construction of a new pile cap to restore the structural integrity of the bridge.

Umahi said government was confident that the repair works would be completed before Christmas, allowing the bridge to reopen fully to traffic.

He explained that following the damage, the government had restricted traffic to one half of the carriageway to reduce the impact on commuters while repair works continued.

“Early this year, part of Eko Bridge’s underwater element was structurally damaged by illegal sand mining, and the dredger got sunken. We decided to allow half of the carriageway for traffic to lessen the problems of commuters on this axis,” he said.

The minister said the government was encouraged that the cracks on the bridge were not progressing, adding that outstanding funds would be facilitated to ensure that the rehabilitation was completed within the targeted timeframe.

He commended the engineers and contractors for their response to the emergency and the progress recorded on site.

The Lagos Federal Controller of Works, Olufemi Dare, and other officials said the projects were also generating employment, supporting local businesses and improving connectivity to major commercial centres around Idumota, Iddo and Oyingbo markets.

The restoration of the bridges is expected to have significant implications for movement of people and goods within Lagos Island and adjoining commercial districts, where prolonged restrictions have compounded traffic congestion and increased travel time for commuters and businesses.

Stakeholders have also renewed calls for greater investment by the federal and Lagos State governments in water transportation as part of a broader strategy to ease pressure on the road network and improve mobility across the state.

The federal government’s decision to compress the Carter Bridge construction timeline and its target of restoring full traffic on Eko Bridge before Christmas underline the urgency attached to the projects, which are critical to the movement of commuters, traders and commercial vehicles across some of Lagos’s most heavily used transport corridors.