Complete Abeokuta-Ibadan Rail Project Before May, FG Orders CCECC

Complete Abeokuta-Ibadan Rail Project Before May, FG Orders CCECC

Kasim Sumaina, Sunday Okobi and Oluchi Chibuzor

The federal government has directed the company in charge of the construction of the Lagos-Ibadan rail project, the China Civil Engineering Construction Corporation (CCECC), to immediately return to site to complete the Abeokuta-Ibadan section of the project before May, 2019.
The government, through the Minister of Transportation, Mr. Chibuike Rotimi Amaechi, gave the directive during the monthly inspection tour of the project at Ologueru, Ibadan, Oyo State, recently.

Amaechi, while speaking to journalists shortly after the inspection of the project, said: “We are ordering the company to return to site now that elections were over.

“They said because of the elections, most of them left the country and they are just returning, so they will need increase the speed of their as they have resumed.

“It is company procedure for them to leave if there is any where they are doing jobs and there are elections. So, they will like to go back to their country and come back after elections.”

On the completion of the entire project, Amaechi said: “Don’t forget that these are phased projects and we decided to start from Ebute Metta which is phase one of the project to Ibadan.

“The phase two is a completely new contract which is from Ebute Metta to Apapa sea port. It wasn’t there before; it was just recently awarded by this government. So, let them finish from Ebute Metta to Ibadan then we can continue from Ebute Metta to Apapa.”

Speaking further, the minister said: “The most important update on the project now is that they should go back to site. There are places that you can see they are doing civil works and we are pushing now that they must complete civil works before the rains and they have promised that by the time we come on the 28th of March, they would have gone far with these civil works.

“Some areas they will complete to what they call MC1 level before they lay the tracks.
“They’ve promised that by March 28, they should be able to get to Kilometre 95 in track laying. We are pushing so that by the first to second week in April, they should be very very close to Ibadan with track laying.”

Amaechi revealed that, “equipment has always been an issue, because it is about gangs. Some gangs don’t have enough equipment.
“If you see kilometres 75 to kilometres 120, you will see that there are gaps and these are the gaps we want them to fill so that we can get to Kilometre 95 and they promised that we can get to Kilometres 95 with track laying but they can’t guarantee up to Kilometer 120.

“But what is important is that if they get to Kilometres 120 with the formation, then we can be sure that before the first week in April we should be able to get there with track laying as 120 to Ibadan is barely 36 kilometres,” he said.

Continuing, he noted that, “there were a lot of new things we didn’t foresee but we met them in the course of construction, and we will go to cabinet meeting to seek approval.”
On the suspension of the three-month free train ride to passengers on the completed section of the Lagos-Abeokuta axis, Amaechi apologised to Nigerians, noting that “it was suspended by the Chinese when they left, and the excuse they gave was that they cannot allow it run because of safety

“Since they have not completed the second line which you have seen that they have nearly completed the second line from nearly Iju to Abeokuta and after that I will insist that they resume because we promised Nigerians and I want to apologise to Nigerians that they had to stop when they left the country because of elections. I didn’t envisage and now I think they should go back to site,” he said.